Shift Handover Template

Build a shift handover sheet: work status, safety, permits and lockouts, equipment status, open actions and staffing, with sign-off lines for both supervisors. Fill it in during the last part of your shift, print it or save it as a PDF, and go through it face to face with the person taking over. Press Next shift and the equipment list and open actions carry across to the next handover.

What a good shift handover covers

  • Who, where and when

    The site, the area or line, the date, the shift and its times, who is handing over and who is taking over.

  • Production and work status

    What ran, what is still running, output against plan, jobs finished and jobs half done. Enough that the next shift can carry on without a phone call.

  • Safety

    Incidents and near misses this shift, permits still open, and every isolation or lockout in place with whose locks are on it. Write None when there were none, so the next shift knows you checked.

  • Equipment status

    Each machine or system that matters, marked running, limited or down, with a short note: what is wrong, who is on it and when it should be back.

  • Open actions

    What the next shift needs to do or follow up, with an owner, a priority and a time. This is the part that stops a job falling between shifts.

  • Staffing and sign-off

    Absences, cover and new starters, any other notes, then names, signatures and times for both supervisors once the handover is done.

Shift handover format: how to fill in the sheet

Start the sheet in the last hour of your shift, not the last five minutes. Fill in the site, area and names, then the work status in a few plain sentences. Press Fill in an example first if you want to see what a complete handover looks like.

Go through safety next: incidents, near misses, open permits and every isolation or lockout. Then list the equipment with its status and the open actions with an owner and a time. Add a row for each item and remove the ones you do not need.

Print the sheet or save it as a PDF, walk the area with the incoming supervisor, and go through it together. When they have read back the open actions and isolations, both of you sign. Press Next shift to start the following handover with the same site, equipment list and open actions.

Planning who works which shift? The shift schedule generator shows a rotating or 12-hour pattern on a calendar.

Keeping a running record of repairs on one machine? Use the maintenance log template.

Shift handover example: what each part looks like

Work status
Line 1 on the 500 ml order, about two thirds done, should finish around 22:00. Pallets for the morning truck are staged at dock 2.
Near miss
Forklift came close to a pedestrian at the dock 2 crossing. Nobody hurt. Cones are out and it is on tomorrow's toolbox talk.
Isolation
Line 2 capper locked out by maintenance, two locks on the panel. Do not restart until maintenance signs it back.
Equipment
Line 2 filler: limited. Running at reduced speed after a nozzle fault. Spare nozzle due on site at 20:00.
Open action
Fit the spare nozzle and bring line 2 back to full speed. Owner: maintenance on call. Priority: high. Due: tonight.
Staffing
One operator off sick on line 3, covered by moving a packer across. Agency packer starts at 18:00 and needs an induction.

Tips for a handover that sticks

  • Hand over face to face

    The sheet is the record, not the handover. Talk it through with the person taking over, so they can ask questions while you are still on site.

  • Walk the floor together

    Where you can, walk the area or the line with the incoming supervisor. Show them the machine that is running slow and the lockout on the panel instead of describing it.

  • Ask for a read-back

    Ask the incoming supervisor to repeat the open actions and isolations in their own words. A gap shows up in a few seconds, before you have gone home.

  • Lead with what can hurt someone

    Start with lockouts, open permits and anything unsafe, then equipment, then production. If the handover gets cut short, the most important part is already said.

More on site meetings and their records: the construction daily report, safety committee meeting minutes, tracking action items.

The handover is spoken. The sheet is typed afterwards.

You just typed this handover up by hand. Next time, tell the incoming supervisor you are recording and record the handover with ParrotNotes on your phone, or record a voice note as you walk the floor before the end of your shift. You get the transcript, a summary and the action items from what was said, to fill the sheet from. The signatures still go on paper.